Project Meeting 2020.06.26

Ben Stabler edited this page Jun 26, 2020 · 15 revisions

Task 1 Project Management (milestone)

  • Discuss comments and revisions to Phase 6a draft scope and cost next time
  • Schedule extension for Phase 5 to end of summer ok, will follow-up with @Bill
  • Discuss plan for online Zephyr tutorial
    • Let's get the website / wiki updates in place by then as well
    • Maybe July too soon with everything going on and the need to finish up active work items and do an official release
    • Let's wait until Phase 5b done so September likely for tutorial; @Joe reply to Zephyr
    • Decide later who can help out with the tutorial
  • Complete first version of SEMCOG model up and running - yeah! @Jilan share visualizer of latest results
  • Move meeting next week from Friday at 11 to Thursday 10

Task 2 Strategic Planning (milestone)

  • Reviewed relevant information from peer projects like matsim, astropy, visioneval
  • Making some progress on the strategic development and contribution plan outline here

Task 3 Two Zones (milestone)

  • Added blending of nearby (maz-to-maz) with taz distances, see the settings.yaml
  • Two zone system setup tested and working, see network_los in the new example settings file
  • Need to work on documentation

Task 9 Estimation Mode (milestone)

  • Working on updating the examples and tutorials to use the example distribution system

Task 10 Support for Three Zone Systems and TVPB (milestone)

  • Support for three zone system inputs working, see configs_3_zone folder
  • Basically done integrating the prototype work we did for SANDAG
  • We're working on the design for downstream models to use the new data structures
  • We're working on building / designing examples (such as expression files, settings, and test example data) to make use of the new data structures
  • @We all think about a more complete test example soon to really exercise performance, memory usage, and other issues