Version 12.7.0

Compare
Choose a tag to compare
@joniles joniles released this 07 Feb 11:43
· 84 commits to master since this release
  • Added support for reading and writing the project property Baseline Calendar Name to and from MPP and MSPDI files.
  • Ensure Start Variance and Finish Variance are read from and written to MSPDI files in the correct format.
  • Improve accuracy of large Work Variance values read from MSPDI files.
  • Add support for the Calendar GUID attribute, which is read from MPP and MSPDI files, and written to MSPDI files.
  • Ensure Activity Codes are available when reading Phoenix PPX files even if they are also being used to construct the task hierarchy.
  • Ensure Activity Codes Values are populated when reading Phoenix PPX files. (Contributed by Rohit Sinha)
  • When writing an MSPDI file, derive the TimephasedData Unit attribute from the duration of the timephased data item.
  • Fixed an issue with the ProjectCalendar.getPreviousWorkFinish method when called with a time which was already at the end of a period of work.
  • Ensure that the proj_node_flag is set for the root WBS node when writing XER files.