Releases: DARIAEngineering/dcaf_case_management
Releases · DARIAEngineering/dcaf_case_management
Baltimore rollout
Snapshot of the rollout to a second fund.
Rails 5, hackathon, fulfillments
Adds a rails 5 upgrade, reporting, fulfillment functionality, some other good stuff.
Release 2: Multiple lines, user administration, external pledges
Adds multiple lines, beginnings of new objects, user administration functionality, and external pledges.
Release 1 DC Line 2016-08-21
First production release. Corresponds to completion of sprints 1-10.
💯
MVP
This release is corresponds to the wet run of the software to take live calls from 2016-07-11 to 2016-07-13.
Design milestone:
- Workflow designed
- User testing round 1 completed
Dev milestone:
- Object hierarchy set up
- Controller hierarchy set up
- Core two views (dashboard and pregnancy edit) established
Admin milestone:
- Site setup and integrated into DCAF architecture
- Deployment pipeline established
- Services set up and paid for