Package to manage activities in a project. This project is inspired by the 'Primavera' or P6 software (Spring in Spanish), hence the name 'Verano' (Summer in Spanish).
- Understand how P6 works under the hood.
- Adding activities one by one in P6 is quite time consuming.
- Provide a Free and Open Source Alternative to P6.
- Enhance my Go coding skills.
# inside a Go module, execute the following command:
$ go get github.com/vanillaiice/verano
- Sort activities in a project based on their relationships (only start to finish relationships supported for now).
- Compute the start and finish times of all activities.
- Render a graph (with graphviz) image file showing the activities and their relationships.
- Parse and process lists of activities in JSON, CSV, and XLSX formats
- Storage of the activities in a SQLite database.
Please check the 'examples' directory in this repo to see these features in action.
For reference, here is the data structure of activities used by this package:
type Activity struct {
Id int // Unique identifier of the activity
Description string // description of the activity
Duration time.Duration // duration of the activity
Start time.Time // Start time of the activity
Finish time.Time // Finish time of he activity
PredecessorsId []int // ID of the activities that precede
SuccessorsId []int // ID of the activities that come after
Cost float64 // Cost of the activity
}