Timeline

All dates are tentative

  • Branch Cut/Feature Freeze: Jan 13th, 2021. Branch cut from 87e8354c4e62a7e28846290cc23cc9aaafe383e4.
  • Kick off: Nov 6th, 2021
  • Community Async Test Week #1: Jan 18th, 2021
  • Community Async Test Week #2: Jan 25th, 2021
  • Code Freeze: Feb 1, 2021
  • Release Date: Feb 9, 2021

Release Managers

Release Notes Draft

For any new, user facing changes targeting Istio 1.9, please add a note below. Examples can be found from the previous release: https://istio.io/news/2019/announcing-1.3/#release-notes. Please format entries following the Release Note Schema.

How do I get my changes into the release?

On TODO, the release-1.9 branch will be created, based on master. Any changes on master before this date will be included in the release. Any changes after will have to be cherry picked.

To get a PR merged into the release branch, it must first be merged into the master branch. PRs can automatically be cherrypicked by typing by adding the cherrypick/release-1.9 label to the PR.

A PR on the release branch will only be approved if:

  • The change is already on master.
    • exception: if a change only applies to the release branch, and should not go to master, a change can be submitted directly to the release branch, but please note this in the PR description.
  • The change is a bug fix, documentation enhancement, or testing enhancement.
    • Changes that are risky may require a feature flag, especially after the 1.9.0 release.
    • Any change not meeting the above, such as a new feature or API, may require TOC approval.

Note: on the istio.io repo, changes should go directly to master until after the 1.9.0 launch. The changes will appear on preliminary istio.io.

Dev Environment

Writing Code

Pull Requests

Testing

Performance

Releases

Misc

Central Istiod

Security

Mixer

Pilot

Telemetry

Clone this wiki locally