Phase 1
- upgrade current installs
- install required modules and get all developers current
- create a feature for uploading images that includes a rating system (we envision this as a large proporiton of time as its something that we have not done before) once completed however feature building will not be as time consuming
- add video upload feature
- split the current document feature so that each group (teachers and students) have separate access
- module integration (word filter, embedded media field)
- theming/interface design decisions
- navigation design
- user roles and groups
- front page theming
Phase 2
- front page build out - public view
- documentation for teachers
- video feature bug fixing
- testing, editing, creating video content
- node translate
- mms upload, email picture upload
- testing
Phase 3
- private blogs/public blog on user landing page
- push to flickr
- sub groups - split original group into 4 sub groups to work on assignments
Phase 4
- Bullet list itemvideo documentations and tutorials
- exhibition planning virtual worlds - this needs to be its own separate project
- technical documentation and packaging for release as open source platform
- promotion for both platform and virtual world exhibit