First test always report a lot of time #51
Comments
Hi @pablorsk, That's frustrating! Let's see what we can find out. Your helpful issue report shows Since Illuminate is a database library, it's very possible Laravel is doing some bootstrapping operations or database creation/hydration before the first case is run. Especially if that code is in My suggestion is to increase the slowness threshold of the first test case, and possibly other test cases that depend on database interaction:
The above code allows for each test case to run for 1000ms before being considered slow. That might give enough time for the database to do its thing. |
You are right, setUp() function take a some time and this time is added to first test time. I don't know if is possible on future separate time from setUp and first test, preventing an incorrect information about time of the first test. This issue, maybe, reports a small bug on library. |
Perhaps not related, but a tip nonetheless: Make sure you don't run migrations/seeds for each test, or even at the start of your test suite. Use https://github.com/drfraker/snipe-migrations to migrate/seed your database, and use transactions whenever you can. |
setUp() method execution is part of the test run because it executes to begin each test case. It is part of the test execution and should be considered for slowness threshold by default. I would be open to accepting a PR for a boolean config flag that decides whether to include setUp() in slowness threshold. I don't have any ideas how to make that happen right now. Maybe each test would need report back to the test suite timer to begin timing, or track execution time up until setUp() method is finished. If you come up with a solution please submit a PR! The base PHPUnit test class
I do not think this is a bug with the library, but perhaps the README could clarify what test code is measured for being slow. A new section like, "Which PHPUnit test methods are considered part of each test execution?" Investigate which methods from Do you still think this is a bug? If so, what action should be taken? |
It seems like the added time for the first test is mostly taken by Laravel to boot the application instance, but for future tests it's already cached so that extra time is not spent. So, what I did was use phpunit bootstrap script pre-instantiate the app instance. This runs before any of the tests are started. It seems to work most :) of the time. Example <?xml version="1.0" encoding="UTF-8"?>
<phpunit xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance"
xsi:noNamespaceSchemaLocation="./vendor/phpunit/phpunit/phpunit.xsd"
bootstrap="tests/bootstrap.php"
colors="true"
>
... Example <?php
require 'vendor/autoload.php';
$app = require 'bootstrap/app.php';
// prewarm the cache (so our tests aren't counted as slow)
$app->make(Illuminate\Contracts\Console\Kernel::class)->bootstrap(); |
First test report allways like a slowly test
For example
You should really fix these slow tests (>80ms)...
Any ideas?
testCool()
has only a simple assert :/I'm using v3.0.0
The text was updated successfully, but these errors were encountered: