How to release the Helm Operator

The release process needs to do these things:

  • create a new release on GitHub, with a tag
  • push Docker image(s) to Docker Hub
  • make sure the version is entered into the checkpoint database so that up-to-date checks report back accurate information
  • close out the GitHub milestone that was used to track the release

Much of this is automated, but it needs a human to turn the wheel.

Overview

The Helm Operator releases use branches and tags with semver versions, like 1.2.3.

Each minor version has its own "release series" branch, from which patch releases will be put together, called e.g., release/1.2.x.

The CircleCI script runs builds for tags, which push Docker images. This is triggered by creating a release in GitHub, which will create the tag.

Release process

Preparing the release PR

  1. If the release is a new minor version, create a "release series" branch and push it to GitHub.

    Depending on what is to be included in the release, you may need to pick a point from which branch that is not HEAD of master. But usually, it will be HEAD of master.

  2. From the release series branch, create another branch for the particular release. This will be what you submit as a PR.

    For example,

    git checkout release/1.2.x
    git pull origin
    git checkout -b release/1.2.1
  3. Put the commits you want in the release, into your branch

    If you just created a new release series branch, i.e., this is a x.y.0 patch release, you may already have what you need, because you've just branched from master.

    If this is not the first release on this branch, you will need to either merge master, or cherry-pick commits from master, to get the things you want in the release.

  4. Put an entry into the changelog

    The changelog is in CHANGELOG.md in the root of the project. Follow the format established, and commit your change.

    If you cherry-picked commits, remember to only mention those changes.

    To compile a list of people (GitHub usernames) to thank, you can use a script (if you have access to weaveworks/dx) or peruse the commits/PRs merged/issues since the last release. There's no exact way to do it. Be generous.

  5. Update the versions in the deploy manifest examples and the Helm chart.

    The example manifests templates are in pkg/install/templates, the Helm chart is in chart/helm-operator. Check the changes included in the release, to see if arguments, volume mounts, etc., have changed.

    Read on, for how to publish a new Helm chart version.

  6. Post the branch as a PR to the release series

    Push the patch release branch -- e.g., release/1.2.1 -- to GitHub, and create a PR from it.

    Note: You will need to change the branch the PR targets, from master to the release series, e.g., release/1.2.x, while creating the PR.

  7. Get the PR reviewed, and merge it.

Creating the release

  1. Create a release in GitHub

    Use a tag name as explained above; semver (1.2.3).

    Copy and paste the changelog entry. You may need to remove newlines that have been inserted by your editor, so that it wraps nicely.

    Publishing the release will create the tag, and that will trigger CI to build images and binaries.

After publishing the release

  1. Put an entry in the checkpoint database

    Add a row to the checkpoint database (or ask someone at Weaveworks to do so). This is so that the up-to-date check will report the latest available version correctly.

  2. Merge the release series branch back into master, so it has the changelog entry and the updated manifests.

    You can do this by creating a new PR in GitHub -- you don't need to create any new branches, since you want to merge a branch that already exists.

  3. Consider releasing a new version of the Helm chart, the process for this is described below.

Bookkeeping

  1. Close the GitHub milestone relating to the release. If there are open issues or unmerged PRs in the milestone, they will need to be either reassigned to the next milestone, or (if unclear where they belong), unassigned.

Helm chart release process

  1. Create a new branch (i.e. release/chart-1.0.0)
  2. Update appVersion with the new Helm Operator version in chart/helm-operator/Chart.yaml
  3. Bump the chart version in chart/helm-operator/Chart.yaml
  4. (Maybe) update image.tag with the new version in chart/helm-operator/values.yaml
  5. Create a PR
  6. After the PR is merged, tag the master with the chart version git tag chart-1.0.0 and push it upstream
  7. CI will build and publish the chart to fluxcd/charts